Progress

Watch Kololi Gardens Grow

Follow the construction timeline of Kololi Gardens, from site prep to the final phase.

March 2023
First Designs

The first designs were presented by the architect

June 2023
Funding

Funding for Kololi Gardens secured

July 2023
Negotiations

Negotiations started with various contractors

August 2023
Designs
Prices Kololi Gardens

Designs completed

September 2023
Sales

Launching of Kololi Gardens Sales

November 2023
Construction
Kololi Gardens Construction

Start of construction work

January 2024
Sold 44%

Already sold

April 2024
Foundation Completed

First foundation completed

May 2024
Sold 70%

Already sold

June 2024
The only way is up

Day in, day out the construction team is adding more and more body to Kololi Gardens

July 2024
M, N, O building top floor completed

These three buildings with studios on the top floors and one-bedroom apartments on all other floors, reached the top floor.  Work in progress!

August 2024
87% sold

Only a handful apartments are now available for sale out to the 120 units. Studios and Penthouse are sold out!

September 2024
Steady progress

The foundations for L building are being laid

October 2024
The last floors are being constructed

The last floors of L building are going up

November 2024
Views from the studios
December 2024
Work in progress
February 2025
Penthouse view - 1 left for sale
March 2025
Let's work on the pathways
April 2025
Let's go up
May 2025
Let's finish the outside walls
June 2025
Let's show off the progres
July 2025
Electrical works ongoing

AC pipe work, connections and electrical work being done

August 2025
Pantry

All apartments with 1 and 2 bedrooms and the penthouses all have a panty which will have a washing machine. 

September 2025
Bathroom tiling and preperations

The bathrooms are being tiled and prepared to install the walk-in shower, wash basin and toilet

October 2025
Ceiling and ceiling lights

The ceilings and the walls have been plastered and have been painted for the first time. LED ceiling lights are installed. 

November 2025
Pool construction has started
Kololi Gardens - pool construction

Central located in the gardens with a separate childrens pool. 

December 2025
And then there were windows

Installation of the sliding window has started

January 2026
Garden works have started

The garden starts to take shape, the walls are being tiled. 

February 2026
Parking spaces being created
Kololi Gardens Gambia

Along the perimeter parking spaces are created 

March 2026
And then there is a pool

Pool works are in full progress

April 2026
painting is about to start

Every day the team works tirelessly towards completing Kololi Gardens 

May 2026
Bathrooms

Installation of bathrooms has commenced. 

June 2026
Some fences have come down
Kololi Gardens Gambia

Kololi Gardens is shaping up nicely. The temporary fence has been taken down, so that the garden team can start their job. 

July 2026
Shaping up

A dedicated team has started with the final works on the grounds of Kololi Gardens. And as you can see, balcony structures are also being fitted. 

October 2026
Kitchens are installed

The completion is approaching now that kitchen installation has begun

November/December 2026
Completion

Completion of Kololi Gardens expected November 2026